00 05 10 15 20 25 30 35
20 years early
Legacy TRU Waste Mission
$8 billion saved
Original Plan
Performance Management Plan (PMP)
28
20
$8B
sites completed early or on schedule
years ahead of original schedule
savings
$3.6B
$2.1B
$1.2B
$0.6B
$0.5B
$16B
$8B
from completion 20 years early
regulatory improvements
TRUPACT-III and rail
mobile/modular equipment
Central Confirmation Facility
100,000
80,000
60,000
40,000
20,000
0
Cumulative waste disposed in cubic meters
00 05 10 15 20 25 30 35
Baseline
Acceleration Plan